
With the sub-floor laid and the plumbing tested there were still myriad tasks before us on the bathroom refurb. I had the ambitious task list prepped for the next two weeks ready but during lunch, Monday, I read through some of the documentation on the tiling adhesives in order to find out how long after laying tiles and grouting we would have to wait to put in the toilet. A mild panic took hold when I read that after the initial 24 hours each for the adhesive and grout to cure only light foot traffic would be allowed for 12 more days. We pushed floor tiling to the top of the list and spent a couple hours per night after work getting a start on it all.

First, we wanted to set the plumbing into the wall with plaster before moving ahead. The first mudding was thick and sloppy and would take a while to set completely.

After work the next evening, I started cutting and setting the cement boards meant to act as the substrate for the floor tiles and some of the wall tiles in spaces left open after removing skirting boards.
Once laid out, numbered, and mapped they were pulled up to lay down some thin-set adhesive, re-set, and screwed into place. Jackie started priming the walls earlier and I moved the scaffold in to sand the ceiling while the backer board adhesive set. There will also be more (finish) plastering once the electrics get installed.

Going into the first weekend, Friday night, I explored the attic above the top floor for the first time. ENORMOUS space (but, access is shitty and it is probably only suitable for long-term storage). Anyway, the ceiling electrics were there and I was able to alter them so that we now have a double switch — one turns on the overhead and the exhaust fan (timered, so it will continue to run 5 minutes after the switch is off); the other turns on the vanity lights and activates a power socket with residual current protection.

The weekend was devoted to tiling. We planned on 2 or 3 hours to lay the floors, starting at noon. Difficult cuts and holes were rife and we finished at 9 pm (7:30, but the cleanup was ENORMOUS).
We had to wait 24 hours before grouting so we took the opportunity to reorganise. Tools had diffused to all bounds of the house and everything was covered in dust from, variously, cutting holes in brick and ceiling, sanding, mixing grout and plaster, etc; some of the dust was kicked down from the attic via the access holes and is almost certainly a century old.
While in the attic, I finished the soil – and grey-water plumbing (which involved cutting new access through the kitchen ceiling causing further delays). We were now missing a key milestone: neither toilet was yet on the new stack but the stack was ready and waiting.
Around 7 pm Sunday, the floor grouting started. Grouting is something of a magic trick wherein you completely obscure — literally, in this case — a pedestrian object then, with a few swipes of the hand, voíla! It is back but enhanced. In our case, we were pleasantly surprised the tiles we chose which have a white grout border dividing the four quadrants took up our black grout filling both the spaces between and within the product. It draws the eye away from our amateurish work and looks frankly marvellous.
At this point — a week into the items in this update 40 calendar days since we bought the tub and toilet — we had consumed about 14½ of our allotted 30 work days. Bruised, abraded, battered and utterly exhausted, I took a day off the refurb although Jackie put in another half day with painting and grout cleaning.
I took annual leave the next day to tile the walls. This was especially difficult as the levelling work was as good as I could get. We will probably have to redo the back in a few years, but the side wall looks okay. Before grouting the walls, the room looks something like an abattoir, albeit one with a nice floor.

Planning on grouting the next evening, Jackie put in a change-order to surround the window with the remaining subway tiles and plans to put in a cornice around the top. So, I focused on building the toilet and attaching the supply fittings to it and the sink. Jackie had the lurgy and painting had, as a result, been back-burnered.
There’s still a lot to do beside the grouting: painting, the tub, a cabinet, the lights, and shifting the sink drain 6 cm so the sink can get hooked up. Soon, but for now there’s a bottle of prosecco waiting.